Support Readiness Claims with Assessment Evidence

Plan a scoped assessment, retain operating evidence and report failures and limitations without overstating conformance.

GovKM-proposed public draft. Published for public review. Not externally accredited or endorsed.

View the EICARS framework resource

Document

Return to the EICARS guidance index

EICARS implementation guidance — proposed public draft. Checklist coverage: V01, V02, V03, V04. Prepared November 9, 2026. These suggested approaches support the published GovKM-proposed EICARS v0.1 draft; they do not add requirements or grant external accreditation.

Purpose and use

Plan a scoped assessment, retain operating evidence and report failures and limitations without overstating conformance.

Use this guide within a declared organizational scope, with existing repositories and suitable organizational processes. AI is optional. Examples and suggested evidence are implementation aids; the published standard governs a conformance assessment. The Riverton case below is fictional, not an observed deployment or test result.

Responsible roles

Assessment lead, domain owners and the accountable approving official; independent review where required.

Assign responsibilities through the organization’s actual instruments. A suggested role in this guide does not itself confer decision authority.

V01 Approve the assessment plan

Suggested approach: Approve the assessment population, expected results, evidence methods, sampling rationale, acceptance criteria and material-failure rules before evaluation. Include all ten requirement domains while documenting conditional instances that do not apply. Risk-based sampling must not be described as exhaustive verification.

Riverton example: Riverton’s plan includes a current briefing, a historical date question, an access denial and an unresolved evidence case. It states which offices, records and routes are tested.

Evidence and completion check: Keep the signed plan and declared coverage. Have a reviewer explain why the sample is appropriate and what conclusions cannot be extended to untested populations.

V02 Examine interview and demonstrate

Suggested approach: Use examination, interviews and safe demonstrations in combination as appropriate. Include ordinary operations, exceptions and prohibited outcomes. Confirm that documented policies correspond to observed behavior. Destructive, adversarial and access checks require approved material and scope; this guide does not authorize production disruption.

Riverton example: Riverton reviews its access policy, interviews the owner and tests an unauthorized synthetic user. The policy alone cannot demonstrate that the search index actually enforces the restriction.

Evidence and completion check: Retain the method, approved test material, expected behavior and observed result. Record conflicting evidence rather than selecting only the most favorable observation.

V03 Record evidence and limitations

Suggested approach: Record the assessor, date, source locations, tested population, sample selection and limitations. Use inspectable evidence sufficient for another authorized reviewer to understand the determination. When reporting counts, name the denominator and unit, such as tested references or selected access paths; avoid an unsupported enterprise readiness score.

Riverton example: Riverton reports that 18 of 20 selected references resolved, names the two failures and limits the result to that sample. It does not claim 90 percent conformance across all requirements.

Evidence and completion check: Retain the assessment record and usable evidence references. Ask another reviewer to reproduce a selected observation and identify where the stated scope ends.

V04 Keep failures and accepted risks visible

Suggested approach: Keep not-demonstrated requirements, unassessed items, missing evidence, approved conditional non-applicability and accepted risks visible. A risk acceptance decision does not turn a failed requirement into a pass. Report a readiness assessment with gaps unless the published draft’s scoped conformance conditions are actually satisfied.

Riverton example: Riverton’s approving official accepts temporary operational risk while an export defect remains open. The assessment still reports that requirement as not demonstrated and limits dependent use.

Evidence and completion check: Retain the determination, rationale, official decisions and corrective actions. A conformance statement must name the proposed draft, scope, date, methods, evidence and limitations, without suggesting external accreditation or AI certification.

Evidence and completion checks

Agree the population, expected results and acceptance conditions before assessing. Record the date, assessor, evidence reference, observed result and limitation. Use approved safe examples for access, malicious-content or lifecycle tests. Documented policy and observed operating behavior are both relevant; one does not automatically prove the other.

On smaller screens, scroll the table horizontally to view every column.

ItemSuggested evidence and demonstration
V01Keep the signed plan and declared coverage. Have a reviewer explain why the sample is appropriate and what conclusions cannot be extended to untested populations.
V02Retain the method, approved test material, expected behavior and observed result. Record conflicting evidence rather than selecting only the most favorable observation.
V03Retain the assessment record and usable evidence references. Ask another reviewer to reproduce a selected observation and identify where the stated scope ends.
V04Retain the determination, rationale, official decisions and corrective actions. A conformance statement must name the proposed draft, scope, date, methods, evidence and limitations, without suggesting external accreditation or AI certification.

Record a gap where the required outcome is not demonstrated. Assign an owner and review date, then verify any correction. Completion of this page alone does not demonstrate conformance with all ten domains, certify legal compliance, approve an AI deployment or authorize autonomous actions.

Common mistakes

Extrapolating a small sample without limits; replacing failures with an average score; calling risk acceptance a pass.

Continue the checklist

Use this page with the EICARS standard, the identity guide and the full Riverton scenario. No particular product, model or repository migration is required.

Implementation overview

Suggested operating approach: assign the responsible roles, confirm applicability, implement suitable controls in the existing environment, examine operating evidence and track unresolved gaps. Tailor the methods to scale and risk. Maintain current services during preparation and preserve records, access and legal obligations throughout.

Standards traceability and references

Government Authority and References

U.S. federal reference review: November 9, 2026. These are GovKM mappings of relevance, not government endorsement or a legal compliance determination. Statutes and regulations are mandatory only within their scope; federal policy applies to covered agencies and uses; technical guidance and voluntary resources require the stated selection, adoption or contractual basis. Private and nonfederal organizations must identify their own governing requirements.

The eCFR is authoritative but unofficial. Retrieved Title 36 pages displayed currency through November 5, 2026. Source retrieval does not establish exhaustive legal currency or clause-level implementation compliance. Check current agency supplements, deviations, court orders, schedules, contracts and later amendments. Add the organization’s actual instruments and the qualified official’s applicability determination.

V01 — Approve the assessment plan

  • NIST SP 800-53A Revision 5 with Release 5.2.0

    Issuing body: National Institute of Standards and Technology. Pinpoint: assessment planning and depth/coverage. Relevance: Evidence plan.

    Classification: Government technical guidance — conditional on selection or adoption. Applicability: Security/privacy control assessment; broader application is an adaptation.

  • OMB Circular A-123 revised March 10 2026

    Issuing body: Office of Management and Budget. Pinpoint: section IV(A)–(B). Relevance: Control assessment.

    Classification: Federal policy — mandatory provisions within stated scope. Applicability: Executive agencies as defined in its Applicability section.

GovKM recommendation boundary: EICARS acceptance rules and scope declarations are proposed. Risk-based sampling does not demonstrate untested populations without stated limits.

V02 — Examine interview and demonstrate

  • NIST SP 800-53A Revision 5 with Release 5.2.0

    Issuing body: National Institute of Standards and Technology. Pinpoint: examine, interview and test methods. Relevance: Assessment methods.

    Classification: Government technical guidance — conditional on selection or adoption. Applicability: Security/privacy control assessment; broader application is an adaptation.

  • 36 CFR 1220.32 and 1220.34 — Records program responsibilities

    Issuing body: National Archives and Records Administration. Pinpoint: 1220.34(j). Relevance: Records evaluation.

    Classification: Regulation — mandatory when applicable. Applicability: Federal agency records within the source’s statutory and regulatory scope. Not a general obligation on private organizations.

  • 36 CFR 1236 Subparts D and E — Federal records digitization

    Issuing body: National Archives and Records Administration. Pinpoint: applicable subpart quality and validation provisions. Relevance: Digitization assessment.

    Classification: Regulation — mandatory when applicable. Applicability: Digitization of temporary or permanent Federal records, according to the applicable subpart.

GovKM recommendation boundary: Applying security assessment methods to all ten information domains is an EICARS adaptation. Tests must stay within authorized scope.

V03 — Record evidence and limitations

  • OMB Circular A-123 revised March 10 2026

    Issuing body: Office of Management and Budget. Pinpoint: section IV(A)–(B). Relevance: Assessment documentation.

    Classification: Federal policy — mandatory provisions within stated scope. Applicability: Executive agencies as defined in its Applicability section.

  • NIST SP 800-53A Revision 5 with Release 5.2.0

    Issuing body: National Institute of Standards and Technology. Pinpoint: assessment results. Relevance: Evidence record.

    Classification: Government technical guidance — conditional on selection or adoption. Applicability: Security/privacy control assessment; broader application is an adaptation.

  • NIST SP 800-53 Revision 5 with Release 5.2.0

    Issuing body: National Institute of Standards and Technology. Pinpoint: CA-2. Relevance: Control assessment.

    Classification: Government technical guidance — conditional on selection or adoption. Applicability: Selected controls, baselines, tailoring and applicable policy or contracts determine obligations. Not every catalog control is universally mandatory.

GovKM recommendation boundary: The specific numerator/denominator format and EICARS assessment record are proposed reporting conventions.

V04 — Keep failures and accepted risks visible

  • OMB Circular A-123 revised March 10 2026

    Issuing body: Office of Management and Budget. Pinpoint: section IV(C), (E), V. Relevance: Deficiencies and reporting.

    Classification: Federal policy — mandatory provisions within stated scope. Applicability: Executive agencies as defined in its Applicability section.

  • NIST SP 800-53 Revision 5 with Release 5.2.0

    Issuing body: National Institute of Standards and Technology. Pinpoint: CA-5. Relevance: Corrective action.

    Classification: Government technical guidance — conditional on selection or adoption. Applicability: Selected controls, baselines, tailoring and applicable policy or contracts determine obligations. Not every catalog control is universally mandatory.

  • NIST SP 800-37 Revision 2 — Risk Management Framework

    Issuing body: National Institute of Standards and Technology. Pinpoint: Authorize and Monitor steps. Relevance: Risk decisions.

    Classification: Government technical guidance — conditional on selection or adoption. Applicability: Security/privacy risk management under applicable Federal policy or voluntary adoption.

GovKM recommendation boundary: EICARS does not equate risk acceptance with satisfying an unmet requirement. That conformance rule is GovKM-proposed, not an external accreditation rule.

This section gives relevant official references for each covered checklist item and is not an exhaustive list of every possible obligation. The actual agency, program, records, data, system and contract determine additional duties. The EICARS organization of these tasks, suggested registers and completion checks remain GovKM recommendations unless independently required or adopted.

Version history

November 9, 2026 — Publication authorized by GovKM. Guidance based on checklist and government authority reference package checked November 5, 2026. References must be periodically revalidated.

November 9, 2026 — Expanded implementation guidance, version 0.1. Replaced the shorter implementation text with the reviewed Riverton examples, task-specific approaches, evidence checks and official authority mappings, with Robert Noyes’s approval. Existing URLs and checklist anchors are preserved. No EICARS requirement or GovKM doctrine is amended.