GAO 27-109529: VA Deployed Its New Health Record at 13 Sites. What Will Guide the Next 26?

VA deployed its new electronic health record system at 13 sites in 2026 and plans 26 more in 2027. GovKM examines how linking schedule milestones, site-readiness evidence, and approvals can strengthen oversight and help AI report rollout status accurately.
A health care implementation team reviews a rollout timeline and site-readiness checklist.
Expand image

What GAO found

The Department of Veterans Affairs deployed its new electronic health record system to all 13 medical centers planned for 2026. It plans 26 more deployments in 2027. In November 18 testimony before the Senate Committee on Veterans’ Affairs, the U.S. Government Accountability Office reported preliminary results from ongoing work. VA had yet to demonstrate that it followed leading scheduling practices. Its integrated master schedule did not cover the full scope of work or include detailed documentation for scheduled activities. GAO-27-109529

GAO said 11 of its 18 prior recommendations had yet to be fully implemented. It reiterated the need to update the master schedule promptly so VA and Congress could understand the tradeoffs involved in completing the rollout. VA program officials told GAO that they were working to integrate site schedules and estimated they would complete the master schedule and supporting documentation by February 2027. Full GAO testimony, pp. 20–23

The Organizational Information Continuity challenge

Can VA reconstruct why a site was judged ready? A rollout date gives staff a point to plan around. The decision to proceed depends on evidence about the work ahead of that date. For example, an interface test may be complete at one site and still open at another. A dependency may be shared across several sites. When the schedule changes or responsibility passes to a new team, the readiness decision must still be traceable to the work, evidence, and authority that supported it.

An AI assistant asked whether a site is ready could cite a scheduled go-live and mark readiness as confirmed even though an applicable test is still open. If the schedule links to evidence at the site and dependency level, a reviewer can trace the answer and see what remains unverified. This is a prospective risk identified by GovKM.

Can later deployment teams tell what prior results actually cover? VA officials told GAO that four Michigan sites were generally meeting the performance targets VA assessed. GAO also reported that the user satisfaction survey for the 2026 deployments was still incomplete. Those observations have different scopes. A later deployment wave needs to know which results came from which sites, over what period, and under which conditions before carrying those conclusions forward. Full GAO testimony, pp. 17–20

An AI summary could generalize evidence from four sites to all 13 or treat a pending survey as completed. The risk is especially relevant when staff use prior results to brief leadership about the next wave. Source-linked results, clear scope, and explicit open items give a reviewer a way to verify each claim.

GovKM’s proposed approach

  1. Maintain one integrated schedule. The program office should link the activities that determine each site milestone, including shared dependencies and work owned by contractors or other teams. Give each tracked activity an owner, predecessor, and completion criterion. Preserve approved baselines and record why milestone dates move. The GAO Schedule Assessment Guide provides leading practices for capturing and sequencing work, tracing dependencies, and maintaining a baseline. 40 U.S.C. § 11302 provides the broader federal IT capital planning and investment control context.
  2. Connect readiness decisions to the evidence available at the time. For each site, link the milestone to the applicable readiness criteria and authoritative records, such as workflow test results, training completion, and unresolved issues. Record who approved the decision, which evidence they relied on, and any conditions or exceptions. Restrict access to supporting records according to agency policy and use approved summaries for oversight reporting where possible. 44 U.S.C. § 3101 establishes the general duty to document agency decisions and essential transactions. The specific evidence and approval process are proposed controls for the agency to assess and adopt.
  3. Carry forward results with their scope and limitations. When one wave informs the next, retain the site, measurement period, data source, and any conditions limiting reuse. Give unresolved findings a responsible owner and link them to the affected schedule activities. Reassess their effect when dependencies, planned dates, or deployment scope change. The GAO Schedule Assessment Guide describes updating the schedule with actual progress and maintaining traceability across levels of work.

OrgAI’s intended role is to help preserve and retrieve those relationships as deployment schedules, systems, and responsibilities change. That capability is in development. VA’s designated officials remain responsible for approving readiness, managing exceptions, and making deployment decisions.

Verify the decision record before the next wave

Choose one completed deployment and one planned site. Ask someone outside the original team to reconstruct which dependencies were cleared, what evidence supported the readiness decision, and which issues were still open. For the planned site, confirm that any readiness condition without current evidence stays visible as unresolved.

Test AI reporting with a planned go-live date, a passing result from a different site, and an unresolved local dependency. The report should keep those facts separate, explain which evidence applies, and leave readiness unconfirmed where the decision record does not support it. The same method applies to a multi-hospital rollout or a statewide benefits system, with readiness criteria and decision authority set by the responsible organization.

GovKM has separately examined how VA can preserve access to legacy records during ERP modernization. In an electronic health record rollout, preserving the basis for each readiness decision gives the next team a record it can use when milestones move and responsibility changes.

Contact GovKM to discuss an assessment of deployment readiness evidence or a pilot for one rollout wave.

RELATED FRAMEWORK DOMAINS

Explore the Connected Framework

Continue through the framework domains connected to this article.

No items found.
RELATED KNOWLEDGE

Continue Exploring

Explore related research, framework domains, and continuity concepts.
CONTINUE WITH THE FRAMEWORK

Explore the continuity relationships that support trustworthy organizational intelligence.

Continue through the GovKM Framework to examine the doctrine, knowledge, and implementation guidance behind Organizational Continuity.